Monday, October 20, 2014

Tail Installation

Vertical fin fitted, leveled, and installed.  Some powdercoat had to be removed and tubing length trimmed slightly for fit. (MHC, EJB)  Hours: 4


Wednesday, October 15, 2014

Cockpit Floor Installation

The cockpit floor was trimmed to fit and then pilot drilled and cleco'd in place. (MHC)  Hours: 0.5

Saturday, October 4, 2014

Flooring

Alum. sheets for flooring of front and rear baggage area were trimmed, fitted, and Cleco'd in place.  Two smaller side flooring pieces were also fitted (next to the seats). (MHC, EJB).  Hours: 4

Rotisserie jig strengthened

Added angle bracket on side of Rotisserie.  Also changed the angle steel piece to a square tubular piece for added strength.  These changes were made to eliminate some swaying of the fuselage from left to right when placed in the jig.  Jig was then repainted (brown and white) (EJB)  Hours: 3