Showing posts with label Jigs. Show all posts
Showing posts with label Jigs. Show all posts

Saturday, October 4, 2014

Rotisserie jig strengthened

Added angle bracket on side of Rotisserie.  Also changed the angle steel piece to a square tubular piece for added strength.  These changes were made to eliminate some swaying of the fuselage from left to right when placed in the jig.  Jig was then repainted (brown and white) (EJB)  Hours: 3

Sunday, September 28, 2014

Rear back baggage panel fitted, airplane on jig

Additional angle had been added at base of jigs for additional stabilization. Fuselage placed back up on jig.  Al sheet was trimmed and fitted for rear baggage panel. This was drilled and is currently held in place with clecos. (MHC, EJB).  Hours: 3


Tuesday, August 26, 2014

Completed Fuselage Jigs

The fuselage jigs were completed and fuselage frame was placed on the rotisserie.  We had to add adjusting feet to the legs of one of the jigs to allow for angle adjustment.  This required TIG welding 3 nuts to the jig legs.  We've also discovered that the garage will have to be re-organized to allow work room. EJB & MHC .  Hours: 4

Wednesday, August 20, 2014

Rotisserie jig bracket construction

Attached front jig spindle to fuselage.  Metal plate and round tubing cut and ground for rear jig spindle.  Metal plate welded to round tubing.   MHC, EJB.  Hours: 1.5

Sunday, August 17, 2014

Jig bracket construction

Cut and welded steel plate to round tubing.  The tubing will insert into the rotisserie jig, and the plate will bolt to a cross bracket that connects to the front of the fuselage. MHC, EJB.  Hours: 1.5

Saturday, August 16, 2014

Jig Bracket construction

Cut and welded square tubing to make a cross-bracket that attaches to the fuselage.  This bracket is needed to connect to the rotisserie jig. MHC, EJB.  Hours: 2

Sunday, August 3, 2014

Rotisserie jig cont.

Finished welding the jig stands, risers, and screw handles.  Painted vertical risers brown.  EJB, MHC. Hours: 1.0

Wednesday, July 30, 2014

Construction cont. for rotisserie jig

Welded long nuts to top (horizontal) pipes on the rotisserie jigs.  EJB.  Hours: 1.0

Saturday, July 26, 2014

Rotisserie jig cont.

Finished and painted 2 bases for jigs. EJB/MHC.  Hours: 1.5

Friday, July 25, 2014

Rotisserie jig construcion

Continued construction of Rotisserie jigs.  Welded 6" pipe to top (moveable) shaft, and tacked nut to a T-handle.  EJB/MHC.  Hours: 1.0

Wednesday, July 23, 2014

Rotisserie jig construction

More work on rotisserie jigs, including welding nuts onto main shaft.  EJB,   Hours:1.5

Tuesday, July 22, 2014

Jig Welding

Grinded and welded on rotisserie jig.  EJB/MHC.   Hours: 1.0

Sunday, July 20, 2014

Rotisserie Jigs

Welded up bases of rotisserie jigs (using TIG).  These jigs are used for holding/rotating the fuselage or wings.   Hours: 2.5,  EJB