Wednesday, January 24, 2018

Wing Fabric Rivet Holes Drilled


The holes for fabric rivets in the top and bottom wing rib caps were drilled with a 1/8" (#30 actually) drill.  The locations were duplicated from previous wing and are detailed  in the March 26, 2017 and April 2, 2017 Blog entries.  We also drilled 1/4" drain holes in the bottom inboard trailing edge of the wing.  Nine drain holes were drilled, each was located 1/2 inch from edge of rib cap, and 1/2 inch from front side of trailing-edge.  Hours: 3

Drain hole

Monday, January 15, 2018

Right Wing Gussets and Fabric Plates

This weekend we made some good progress on fabric backing plates and gussets for the right wing.  There is a fabric plate at each point where a cable exits the wing to control the flap or aileron, and additional plates are located at the lift-strut attach brackets.  The fabric backing plates were trimmed carefully around the cable exit points and deburred, then they were clamped in place temporarily while we drilled holes for the rivets.  We used a hole-locating tool (which we had previously made when working on the left wing) to match the hole in the fabric plate to the holes that were already drilled in the lift-strut brackets.  Additional holes were drilled for nut plates that will be used to fasten cover plates on the bottom side of the wing.  All holes were deburred and the ones that require flush-mount rivets were dimpled.  Unfortunately, we didn't have enough nut plates so couldn't finish up the two fabric plates that needed them.  We ordered some more from Aircraft Spruce and will finish those up when they arrive.  We will epoxy all fabric plates on the top-side of the wing once those are completed.

Three fabric backing plates

Fabric plate for lift-strut at leading edge


While we had the wing oriented upside right, we  installed the fabric plate for the upper aileron hinge point. Since no nut-plates are needed for that fabric plate, we went ahead and attached those permanently (Using Hysol epoxy and small alum. rivets). 

Fabric plate for Aileron
We installed small wood gussets for the right wing.  We turned the wing onto the leading edge and clamped it vertically so that the gussets would not move while the epoxy was curing.  Surfaces were cleaned, then these gussets simply epoxied in place.  After the epoxy had cured 30 minutes, the fillets were smoothed with a wet finger.  Hours: 5.0
Wing tipped up vertically and clamped in place

Two gussets epoxied in place



Thursday, January 11, 2018

Aileron/Flap Pulley Install

With a little luck and a lot of fidgeting, we were able to get the three pulley brackets aligned and installed. Like on the left aileron, we joggled the top control horn for better alignment.  We used the same procedure as before and it worked wonderfully.

After the brackets were aligned correctly, the rivet holes were drilled, deburred and the brackets were riveted and epoxied in place. Hours: 4

Joggle in Aileron Control horn for Alignment

Aligning the top Aileron Pulley

Flap Pulley Bracket installation Complete

Top and Bottom Aileron Pulley Brackets Installed

Monday, January 1, 2018

Aileron, right wing

The aileron needed 30 deg down deflection from neutral position, but we were only getting 25 degrees.  We trimmed a little bit of fiberglass at the front edge of slots in the aileron leading edge that were hitting the hinge, and that helped get us to 29 degrees deflection.  At this point, we ran into another issue as the fiberglass no longer interfered, but one half of a new aileron hinge bracket that we made was now interfering.  We noticed that when we made this aluminum hinge bracket, it was slightly wider than the one we replaced, so we filed down the edge slightly which gave us more clearance.  Once we corrected this, we were able to get close to 32 degrees deflection down, which is sufficient. 

We also began planning for installation of the aileron pulleys on the right wing.  We clamped the lower pulley in place temporarily, and need to check alignment carefully before drilling any holes.  We ran into alignment issues on the left wing that required us to make a new bracket, and may run into similar issues with the right wing.   Hours 2.0

Thursday, December 21, 2017

Fuel Tank Gap Rib Final Install

After cleaning and sanding the mating surfaces, the Fuel Tank Gap Rib was epoxied and riveted in  place using the Hysol structural epoxy.   A section of cap strip between the Gap Rib and the leading spar was carefully cut to size.  After sanding and cleaning the cap strip and fiberglass tank the cap strip was epoxied and held down with weights until the epoxy cured overnight.

Fuel Tank Gap Rib and Cap Strip Epoxied in Place
Next we started gathering the parts for attaching the aileron pulley assemblies.  We checked the aileron deflection with a angle meter, checking for 30 degrees either way.  We noticed we easily get the 30 degree down deflection, but having to tweak the opening on the fiberglass aileron leading edge to allow full 30 degree up deflection.  We're trying not to remove too much material, so it's a tedious on/off process  to slowly creep up on a little more than 30 degrees.  Hours: 3

Measuring Aileron Up/Down Deflection

Monday, December 11, 2017

Fuel tank gap filler rib

A short rib that will be attached between the fuel tank and the trailing edge (providing a surface for fabric attachment) was readied for installation.  It will be installed half way between the ribs that are on each side of the fiberglass gas tank.  The rivet holes for attachment were drilled, and the trailing edge aluminum was dimpled for counter-sunk rivets.     Hours: 0.5

Sunday, December 10, 2017

Right wing flap and aileron hinges

Installed the flap and aileron hinge plates for the right wing.  We were more careful this time when drilling through the ribs for the flap hinges by drilling through one hinge plate and the rib before lining up the 2nd hinge plate.  This helped guarantee that no holes were accidentally drilled off center, as we didn't really want to make another hinge if we didn't have to.

The hinge plates and mating surfaces were scuffed and cleaned, and then were epoxied and riveted in place.  Below is a picture of one of the hinges.  Six hinges total were installed (three on both the aileron and flap for the right wing).   Hours 3.5

Aileron hinge riveted and epoxied in place



Wednesday, December 6, 2017

Right Wing aileron hinge

Drilled holes through the right wing ribs for attachment of the aileron hinges.  Made a mistake on one bracket as the two halves of the hinges did not line up perfectly when drilling, so created oblong holes on one of the hinge plates.  We fixed this by making a new aluminum hinge bracket from 0.063 aluminum.  The manual says to simply swing one bracket plate out of the way before drilling, but that's not as simple as it sounds with everything attached and clamped in place.  Hours 1.5

Tuesday, December 5, 2017

Flap/Aileron Alignment

We continued working on the alignment of the right flap and aileron.  We used 1/8" shims between the wing trailing edge and the flap/aileron.  We had to check at various points since this measurement varies along the trailing edge.  We also made sure the attach brackets were centered on the ribs top to bottom and they were clamped in place.  Hours: 1

Saturday, December 2, 2017

Aileron/Flap Mount Bracket

 Holes were cut in the wing trailing edge to accept the Aileron and Flap mounting brackets.  Like on the previous wing, the holes locations were marked and then cut using a vibrating multi-tool.  This left a very narrow hole.  The holes were widened using a Dremel Cutoff wheel followed by round and straight files.

Holes cut in wing Trailing Edge
 We started aligning the the flap and aileron on the wing.  We still have more fidgeting with the location before drilling.  Hours: 3

Aileron/Flap location has begun

Thursday, November 16, 2017

Right Wing Trailing Edge installation

Cleaned, epoxied, and riveted the aluminum trailing edge onto the right wing.  Care was taken to clean epoxy from the rib areas where the hinges will be later installed before it cured.  This was something we didn't pay close enough attention to on the left wing, which meant we had to take extra time later on to sand down dried epoxy on that wing.  After about 60 minutes of curing time, we smoothed the epoxy fillets.  Hours: 1.0
Trailing edge installed on right wing

Monday, November 13, 2017

Right Wing Trailing Edge

The next step is to epoxy the right wing trailing edge aluminum pieces. Before we can do that we need to prepare the mating surfaces. The areas were marked and then abraded. Hours: 1.0

Sunday, November 12, 2017

Flap/Aileron Cable Guides

The holes in ribs 1 through 7 were drilled using templates.  Like on the left wing, we had to use "corrected" templates obtained from the Just Aircraft forums on http:\\www.wingsforum.com . The final holes were drilled at 5/16" and the required 2" piece of tubing was installed in each hole location.  Hours 1.5

Cable Guides drilled and Installed

Sunday, November 5, 2017

Lift Strut Attach Brackets for Right Wing

A plethora of holes for the two lift strut attach brackets were previously drilled, and the brackets were cleco'd in place.  We removed the brackets, deburred all the holes, and cleaned/abraded the mating surfaces to get ready for epoxy.  We then epoxied and riveted the two strut brackets to the spars.
Lift strut bracket at leading edge of right wing
The center rivet on the back bracket was difficult to set because of a center brace that gets in the way.  We got around this problem by making a small wedge with a hole in the center.  We bent a rivet stem at first just to get the rivet into its hole, and then fed the rivet stem through the hole in the wedge.  The wedge then allowed us to use the rivet gun at a slight angle so that we could access and pull the center rivet.   We fought with this rivet for a while at first, but the job was much easier once we used the metal wedge Hours: 3.5
Strut bracket, with small wedge tool shown



Wednesday, November 1, 2017

Drilling Strut Attach Bracket Holes

Drilled all the holes in the two Strut Attach Brackets.  Cleco's were placed in approximately every other hole.  Hours: 1
Strut Attach Brackets Drilled & Cleco'd